DEVELOPMENT ALLOWANCE AUTHORITY ACT 1980 (ARCHIVE)

CHAPTER 2 - DEVELOPMENT ALLOWANCE  

PART 2 - KEY CONCEPTS RELATING TO PROJECTS  

Division 6 - Substantial commitment to completion of a project  

SECTION 20 (ARCHIVE)  

20   SUBSTANTIAL COMMITMENT TO COMPLETION OF A PROJECT - RELEVANT FACTORS  
In determining whether a substantial commitment to the completion of a project has occurred, or is reasonably likely to occur, before a particular date, the DAA must have regard to:


(a) in any case:


(i) the physical work that has been undertaken in carrying out the project before that date; and

(ii) the nature of the contracts that have been entered into before that date in relation to the project; and

(iii) in the case of a project consisting of the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facility or facilities; and

(iv) such other matters as the DAA considers relevant; and


(b) if the project is part of a joint venture project:


(i) the physical work that has been undertaken in carrying out the joint venture project before that date; and

(ii) the nature of the contracts that have been entered into before that date in relation to the joint venture project; and

(iii) in the case of a joint venture project consisting of the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facility or facilities; and

(iv) such other matters as the DAA considers relevant; and


(ba) if the project is part of a joint venture project scheme:


(i) the physical work that has been undertaken in carrying out each other joint venture project to which the scheme relates before that date; and

(ii) the nature of the contracts that have been entered into before that date in relation to each other joint venture project to which the scheme relates; and

(iii) in the case of a scheme which involves the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facilities; and

(iv) such other matters as the DAA considers relevant; and


(c) if the project is part of a company group project scheme:


(i) the physical work that has been undertaken in carrying out each other project to which the scheme relates before that date; and

(ii) the nature of the contracts that have been entered into before that date in relation to each other project to which the scheme relates; and

(iii) in the case of a scheme which involves the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facilities; and

(iv) such other matters as the DAA considers relevant; and


(d) if the project is part of an individual project scheme:


(i) the physical work that has been undertaken in carrying out each other project to which the scheme relates before that date; and

(ii) the nature of the contracts that have been entered into before that date in relation to each other project to which the scheme relates; and

(iii) in the case of a scheme which involves the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facilities; and

(iv) such other matters as the DAA considers relevant.

 

Disclaimer and notice of copyright applicable to materials provided by CCH Australia Limited

CCH Australia Limited ("CCH") believes that all information which it has provided in this site is accurate and reliable, but gives no warranty of accuracy or reliability of such information to the reader or any third party. The information provided by CCH is not legal or professional advice. To the extent permitted by law, no responsibility for damages or loss arising in any way out of or in connection with or incidental to any errors or omissions in any information provided is accepted by CCH or by persons involved in the preparation and provision of the information, whether arising from negligence or otherwise, from the use of or results obtained from information supplied by CCH.

The information provided by CCH includes history notes and other value-added features which are subject to CCH copyright. No CCH material may be copied, reproduced, republished, uploaded, posted, transmitted, or distributed in any way, except that you may download one copy for your personal use only, provided you keep intact all copyright and other proprietary notices. In particular, the reproduction of any part of the information for sale or incorporation in any product intended for sale is prohibited without CCH's prior consent.