In determining whether a substantial commitment to the completion of a project has occurred, or is reasonably likely to occur, before a particular date, the DAA must have regard to:
(a) in any case:
(i) the physical work that has been undertaken in carrying out the project before that date; and
(ii) the nature of the contracts that have been entered into before that date in relation to the project; and
(iii) in the case of a project consisting of the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facility or facilities; and
(iv) such other matters as the DAA considers relevant; and
(b) if the project is part of a joint venture project:
(i) the physical work that has been undertaken in carrying out the joint venture project before that date; and
(ii) the nature of the contracts that have been entered into before that date in relation to the joint venture project; and
(iii) in the case of a joint venture project consisting of the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facility or facilities; and
(iv) such other matters as the DAA considers relevant; and
(ba) if the project is part of a joint venture project scheme:
(i) the physical work that has been undertaken in carrying out each other joint venture project to which the scheme relates before that date; and
(ii) the nature of the contracts that have been entered into before that date in relation to each other joint venture project to which the scheme relates; and
(iii) in the case of a scheme which involves the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facilities; and
(iv) such other matters as the DAA considers relevant; and
(c) if the project is part of a company group project scheme:
(i) the physical work that has been undertaken in carrying out each other project to which the scheme relates before that date; and
(ii) the nature of the contracts that have been entered into before that date in relation to each other project to which the scheme relates; and
(iii) in the case of a scheme which involves the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facilities; and
(iv) such other matters as the DAA considers relevant; and
(d) if the project is part of an individual project scheme:
(i) the physical work that has been undertaken in carrying out each other project to which the scheme relates before that date; and
(ii) the nature of the contracts that have been entered into before that date in relation to each other project to which the scheme relates; and
(iii) in the case of a scheme which involves the expansion, improvement or upgrading of a productive facility or facilities - the physical progress made before that date in relation to the installation of new plant for use in the expanded, improved or upgraded facilities; and
(iv) such other matters as the DAA considers relevant.